Day 98: End of Week 14
Thursday, January 30, 2014
Day 97: Pre Drywall Orientation
Today I met with Raymond, the construction superintendent, for my Pre Drywall Orientation. Basically we went over what had been done so far, where we are on the timeline, and what to expect from here on.
Wednesday, January 29, 2014
Day 96: Foam, Spray, Security... Oh My!
Today we found more supplies delivered for the driveway. When we ventured inside, we saw the house had been foamed sealed and then sprayed with some sort of blue stuff which I've since learned is called Bora Care. Its a required termite preventative that all FHA backed loans must have done. It makes the wood completely untouchable by termites. Sweet, right?! I also noticed the house had its security system installed. We saw some new pieces installed on the ceiling as well as a couple of attic vents. The braker box appears to have gotten hooked up, too. And my kitchen island has been reinforced. The kids found that they had drywall in their rooms so we couldnt walk around much. We found a few more random pieces to add to our treasure box, too.
Tuesday, January 28, 2014
Day 95: Iced Again
School was cancelled again today. We finally crept out of the house around 2pm once the ice melted. I still see some on the rooftops. No one is here working today. Can't blame them either. It's only 35 degrees out.
Monday, January 27, 2014
Day 94: A Look at the Process Map
Sunday, January 26, 2014
New Neighbors!
The girls and I also took our dog to the Bark Park today where we ran into our other new neighbors, Mike and Esther! Small world? Or maybe God just wants us to be good friends. It was nice seeing them, and meeting two more of their dogs. Its times like these when I am happy Georgetown is still "small town".
Saturday, January 25, 2014
Friday, January 24, 2014
Day 91: Electrical Roughed In
Went over to check out the house and discovered ice! The water in the tubs was frozen. There was ice on the glass windows and icicles on the tension rods that still stick out of the slab. The girls thought that was cool to see.
We also noticed there were a lot of piles of brick. That will be really neat to see going up. There are outlet boxes in all the rooms and switch boxes where out light switches will be. You can see the breaker box in the one pic below.
Thursday, January 23, 2014
Day 90: First Ice
I see we also got brick delivered!
Wednesday, January 22, 2014
Day 89: Standing Water in Kitchen
I also asked him what they do for the pipes when we have freezing weather, which we're supposed to have tomorrow. He advised that they would turn the water off and drain the line so that the pipes don't burst. I was glad to hear that!
Not much else is going on here. I did see that the main house is shingled, porches not yet. I didn't take a picture but will tomorrow and post it back here.
Tuesday, January 21, 2014
Day 88: Fixing the Problem
In other related news, I heard from Jaime today about locking in an interest rate. Ive locked in and have a closing date tentatively set for March 26th!
The plumber installed the tubs and shower yesterday however I was pretty unhappy at the time and didn't bother snapping a pic so I did today. And, we got shingles delivered today!
Monday, January 20, 2014
Day 87: The Puddle
Sunday, January 19, 2014
Day 86: Caulking & Painting
Another big change today--they're caulking and painting! Very exciting to drive up and see. It looks so amazing!